Hove
A former Jaguar Land Rover dealership. Demolition and site clearance works with new construction of a 4 storey self storage facility including double basement and flexi offices. Target to achieve Breeam Excellent accreditation with green roof, roof mounted solar photovoltaic arrays and electric vehicle chargers.
- Main Contractor: Mclaren Group
- Construction Site Manager: Dale Burton
- Store Opening Date: 21st March 2022
2018

April
Site acquired April 2018
2020
August
Demolition in progress 6th August 2020
2020
October
Demolition complete
2020
November
Shell construction works begin
2021
End of March
The bulk excavation of the site is now complete, this will form our basement level.
Whilst excavating we unearthed the previously known historical rail cutting which dates back to 1898, this ran though the site until the 1950’s, at which point it was back filled and the site was then redeveloped.
2021
April
Works are progressing to complete the structural slab to the basement prior to the reinforced concrete walls to the perimeter.
2021

May
Attenuation Tank going in, this will eventually be buried under the car park area.
2021
May
The 3 stages of the perimeter reinforced concrete wall can be seen in this photo. Steel reinforcement has been installed to the left of the photo before the temporary support framework is erected prior to the concrete pour on the right of the photo. Finally moving back across to the left, the finished concrete wall lining can be seen.
2021
Early July
The rain might have fallen but this hasn’t held up progress to install the steel reinforcement for the remaining ground floor section, whilst in the distance the main steel frame has commenced.
2021
September
Steel frame nearing completion.
2021
November
Shell almost complete.
2021
29th November
Fit out works start.
2022
21st March
Store opens.