The Property team approached Careys in July 2018 to acquire Tower Business Park in Wembley, approximately 500m from the stadium. There are three separate industrial units, two storeys high with a footprint of 27,639 sq ft. During WW2 buildings were constructed across the entire site; these were subsequently demolished in 1991 with the current buildings being constructed in 1999.

The site occupies a prominent island plot of approximately 1.0 acres and is located in a predominantly industrial area.

Big Yellow completed the purchase of the freeholds by February 2019. The new store proposal is for a self storage facility with  approximately 70,000 net sq ft MLA.

The redevelopment proposals were submitted to the local planning authority on 12th May 2020 with consent for the new store granted on 25th August 2020. We are targeting a Breeam accreditation of Excellent.

Construction activities to start once Vacant Possession obtained in Summer 2024.

Nigel Hartley, Big Yellow Construction Director
 

  • Architect:  Cornish
  • Engineer:  Evolve
  • Project Manager & QS: Paragon
  • Principle Designer (Health & Safety):  RGP Development Services
    M&E Services:  TFT

Target Programme
Construction complete: 02/03/26
Store Opening Date: 09/03/26

  •  

2018

 

Wembley existing site.JPGSummer

Existing site

2018

July

The property team approached Careys

2019

February

Freehold purchased

2020

May

Redevelopment proposals submitted 

2020

August

Consent granted

2024

Wembley Demolition started.JPG

19th July

Phase 1 Demolition has started

2025

Wembley Demolition nearing completion.JPG

January

Phase 2 Demolition nearing completion

2025

24th February

Our Main Contractor MCS Group starts on site

2025

Wembley attenuation tank installation.JPG

April

Attenuation tank being installed

2025

Wembley foundations laid.JPG

April

Foundations have been laid

2025

Wembley Steel frame being erected.jpeg

May

Steel frame being erected

2025

Wembley brick and blockwork being laid.jpeg

June

Brick & blockwork being laid

2025

Wembley Roof & Walling cladding going up.JPGJuly

Roof & Wall cladding going up

2025

Wembley Glazing installation.jpegJuly

Glazing being installed

2025

Wembley Oversite slab being laid.JPGAugust

Oversite slab being laid

2025

Wembley Mezzanine floors being erected.JPGSeptember

Mezzanine floors being erected

2025

Wembley Envelope of the building now finished.jpegNovember

Envelope of the building now finished

Store Opening

Mar 26