The Property team first identified the requirement for a second store on the western side of Slough’s Town centre in September 2017. Having considered the former Trade Sales Motor Showroom, the Acquisition team settled on the Northgate Vehicle Hire and Van Monster Depot on the opposite side of the road.

The site is approximately 2 acres and located two miles from the existing Slough store, which opened in 2000. Previous uses include light industrial warehouses and a petrol filling station which are no longer evident. The site is largely a vacant plot currently used as a hardstanding for cars with a temporary portacabin.

Big Yellow completed the purchase of the freehold in April 2019. The new store proposal is for a self storage facility of approximately 90,200 sq ft MLA.

The planning application for the new building was submitted to the Council on 19th March 2021 with Planning Consent received on 5th November 2021. Section 73 Application to vary the consented elevations was approved on 10th October 2022.

Nigel Hartley, Big Yellow Construction Director
 

  • Architect:  Mountford Pigott
  • Engineer:  Campbell Reith
  • Project Manager & QS: Paragon
  • Principle Designer (Health & Safety):  RGP Development Services
    M&E Services:  Silcock Dawson

Target Programme
Shell Construction: to start Q1 2023
Fit out due: to commence Q1 2024
Store Opening Date: 16/02/26

  •  

2022

SLough Bath Rd existing site.jpg

 

Spring 

Existing site

2022

Spring / Summer 

Site clearance and enabling works

2022

Slough Bath Road Demolition complete.JPG
July

Demolition complete

2024

14th October

Toureen our Main Contractor starts on site

2024

Slough Bath Road Attentuation Tank.jpg

 

October

Attenuation tank being installed

2024

Sough Bath Road Foundations being laid.jpg


October / November

Foundations being laid

2025

Slough Bath Road First Steels up.JPG


January

First steels going up

2025

Slough Bath Road steel frame complete.jpg


March

Steel frame complete, roof panels being installed

2025

Slough Bath Road brock and blockwork installation.JPG


April

Brick & blockwork being installed, this photo also shows that the ground floor slab has been raised

2025

Slough Bath Road cladding panels and back slip installation.jpg


June

Cladding panels & brick slips being installed

Store opening

Feb 26