• Epsom

    Epsom

  • Epsom

    Epsom

Epsom

The Property team first considered the site’s potential in this affluent historic market town in Summer 2018. Big Yellow’s initial bid was unsuccessful however post pandemic, the site was remarketed and eventually acquired in January 2021. The existing buildings are operated as a Majestic Wine warehouse with the adjacent Office Outlet recently vacated.

The site of the new store is located on East Street with the High Street less than 500m away. In the mid 19th century the site was partially occupied by open land and trees with a row of residential properties added around 1896. The current warehouse building with car parking was constructed in 1983 and remained largely unchanged until the present day. Adjacent the property is a Gas Works, decommissioned in 2013 with student residential properties developed adjacent by 2020.

The new store proposal is for a self storage facility with flexi offices totalling 58,000 net sq ft MLA at ground floor level plus four floors of storage.

The redevelopment proposals were submitted to the local planning authority in September 2021. We are targeting a BREEAM accreditation of Very Good.

Demolition and site clearance works are due to start once planning approval is obtained for the redevelopment.

Nigel Hartley, Big Yellow Construction Director
 

  • Architect:  Cornish Architects
  • Engineer:  Campbell Reith
  • Project Manager & QS: Colliers
  • Principle Designer (Health & Safety):  RGP Development Services

Target Programme
Shell Construction: Commences February 2025
Store Opening Date: May 2026

  •  

2022

Spring / Summer 

Site clearance and enabling works

2023

Summer 

Shell Construction provisional start date

2024

Spring 

Big Yellow Fit Out due to commence

2024

Epsom IMG_9544.JPG
September

Demolition works commence and are expected to be completed in January 2025.

2024

Epsom IMG_9700.JPG
December

Demolition works of the building along the northern boundary near completion. Works were carried out in agreement with the neighbours to ensure minimal disruption.

2024

Epsom IMG_9708.JPG


December

Demolition of the main building, now complete ready for the next stage to remove the slab and foundations and commence crushing.

2025

Epsom installation of the piles.jpg


February

The main works have now commenced, starting with the installation of the piles.

2025

Epsom Steel Frame aerial shot.JPG


May

Works to erect the steel frame are now well underway as you can see from this aerial shot.

2025

Epsom Steel frame errection.jpg


June

Works to erect the steel frame are progressing well, with the frame due to be completed in the next 2 week.

2025

Epsom Steel frame almost complete.jpg


July

The steel frame is now complete other than a small section to allow the roofing materials to be craned onto the roof.

2025

Epsom Roof Cladding works progressing.JPG

 

August

Roof cladding works are progressing well, and the infill section of steel frame is complete.

Store opening

May 26